Pre-interview: written from public sources only. LARN hasn't spoken with Vast, and the reasons for the speed-up below are Vast's stated practices or our inferences until we do.
Short answer: On Oct 29, 2026, Vast, the Long Beach-based commercial space station company, said Hull 3, a qualification structure for Haven-1, its first planned commercial space station, was "manufactured, inspected, and proof tested ... in-house in Long Beach in five months, four months faster than Hull 2, the flight structure" (@vast). That headline compares a test article with a flight article. Compared like for like, qualification hull to qualification hull, it's closer to six months down to five. That's real progress. Our hypothesis is that integration explains part of it, probably not all. Only Vast can say.
The numbers, like for like
- First qualification hull: "six months," per Vast's Feb 2025 update (Vast).
- Hull 2, the flight structure: about 9–10 months, against a six-month plan. Our reading is that flight hardware carries heavier inspection and paperwork, which may explain part of the gap.
- Hull 3, the new qualification hull: five months.
The hull numbering behind this comparison is our inference. Vast was also claiming "under six months per hull" in early 2025 (same update). So Hull 3 may show a process recovering after a slow flight build, rather than a steep learning curve. The source is one X post, and there's no press release.
Why is Vast building hulls faster?
We don't know yet. These are Vast's stated practices, and how much each contributed is what we'd want to ask:
- In-house milling, rolling, welding and inspection at its Long Beach headquarters.
- Its own test stand in Mojave, with 36 hydraulic actuators and 64 strain-gauge channels (Vast).
- A make-vs-buy rule. CEO Max Haot: outsource where you can, and "only go in-house if you need a quicker timeline or it's a complex part" (NASASpaceflight).
- Rate-production leadership. VP of Manufacturing Shane Cioni came from Falcon 9, Virgin Orbit and Relativity (Vast team).
Why it matters
- COOs: the useful number isn't one hull's time. It's the learning rate per hull, and what resets it (a design change, a new weld process, a staff change). That's the metric to ask any hardware supplier for.
- Scaling founders: this is a lesson in telling a production-speed story that holds up. Compare like for like, say what's included, and separate test articles from flight articles.
- Investors: NASA's Commercial LEO Destinations (CLD) Phase 2 proposals are due Dec 8, 2026, with an award expected Apr 15, 2027 (NASA). Production-rate claims will matter in that race. Competitors' hull cycle times aren't public, so there's no fair comparison yet.
Haven-1 is targeted for early 2027 on a Falcon 9 (Aviation Week); that's a company target. One secondhand risk: Crew Dragon availability for commercial stations (The Space Review).
What we'd ask Vast
Vast's VP of Manufacturing, Shane Cioni, is the person best placed to answer. We haven't spoken with him yet.
- Where did the month come out: machining, rolling, welds, inspection, or test prep?
- What does "five months" cover, start to finish?
- What's the learning rate per hull, and what resets it?
- How fast could a crewed pressure hull be built and qualified, and what sets the floor?
Your turn: if you've run hull or pressure-vessel lines, reply and tell us what sets the floor on build-and-qualify time. Follow LA Robotics Network for the interview if it happens.